Building permits are one of the few public windows we have into what's coming: they indicate what will be built, though not when or if it will sell. I'll tell you what the most recent data I found says and, most importantly, how to read it without drawing too many conclusions.
According to an Acento note from July 31, 2026, citing data from the Ministry of Housing for the second quarter (April to June):
✔ At the national level: RD$175,829.75 million in investment valued in buildings and 479 building permits issued.
✔ La Altagracia: RD$58,773.9 million in investment, nearly a third of the national total (about 33.4% by my calculation). It is the province with the highest investment for the quarter, ahead of Santo Domingo (RD$49,465.8 million) and the National District (RD$30,977.9 million).
✔ By use, at the national level: 73.49% of permits were residential projects; in investment, residential totaled RD$93,343.3 million (around 53%) and lodging RD$39,448.2 million.
✔ Average time for a building license: 165.95 days, according to the same note.
This is the most important part:
✘ They don't report how many permits correspond to La Altagracia, only the investment.
✘ They don't separate how much of the province's investment is housing and how much is lodging. The breakdown by use is national. With so much hotel activity in the area, I can't assume it's housing.
✘ They don't bring square meters or number of units.
✘ They don't compare to another quarter or year, so I don't know if it's going up or down.
✘ A permit is not a completed work. It can be delayed, changed, or not executed.
✘ Valued investment is not sales price: it's the estimated value of the work.
✘ They say nothing about demand, that is, whether those units will sell or be rented.
The note indicates an average license timeframe of nearly 166 days, while the Ministry of Housing has talked about an objective to issue licenses in 30 days. These are different things: one is an observed average and the other is an announced goal. We'll have to see if the average drops in subsequent quarters.
High activity doesn't mean prices going down or up. It depends on demand, which permits don't measure.
Look at the type of future supply, not just the volume: apartments, villas, hotels, mixed. If you know that a project near yours has a permit, research its typology and price.
Look at the specific area: the provincial figure mixes Bávaro, Punta Cana, Cap Cana, Higüey, and other zones.
Review the expected delivery timeline of the projects that compete with yours.
Combine with other signals: occupancy, flights, actual rentals and sales speed.
✔ The quarterly figures from the Ministry of Housing and the National Statistics Office, when they publish them.
✔ The license and permit status of a specific project, through your lawyer, as we saw in the article on verifying municipal permits.
✔ From your agent, how many competing projects are in the area and in what phase.
Permits tell you there's confidence and capital moving in La Altagracia. They don't tell you if there will be oversupply or if your prices will hold. Use them as one more signal, and compare it with actual sales and rental data.
If you want to talk about how to read future supply in your area of interest, write to me. I'm Yolanda Landínez and I'd be happy to accompany you: write to me on WhatsApp.
Informational content, does not constitute financial advice. Figures from a news article citing data from the Ministry of Housing; verify in the official source.
Source: Acento, 31/07/2026